Development/Splice length for reinforced concrete?

For anyone who's done any concrete design/detailing, I've got a question about how you handle a particular situation. I have a simple span box-girder bridge with a composite concrete deck. Traditional deck design (not empirical), 4 layers of reinforcement in the slab. The span length requires that I splice the longitudinal deck bars. Which development/splice provision is appropriate here? Since it is a simple span, the bars aren't tension bars, they're in the compression zone for the member but aren't there for strength, they're really just temperature/shrinkage bars.

更新:

Applicable design code is AASHTO LRFD.

2 個解答

相關度
  • 5 年前
    最愛解答

    The code calsl for a minimum overlap of splices regardless of the load on the re-enforced concrete. I don't remember the amount of over lap but it is something like 10 or 20 diameters of the rebar size.

  • 4 年前

    What kind of engineer are you? You really can't figure this one out? Did you get your degree in some third world country?